BNSF Retaining Wall 5.30N
scope of work
- 55' Long Piles
- Installed Along Active Railway
SERVICES
Earth Retention
WORK COMPLETED
December 2019
Project Summary
Stalworth installed 26 drilled soldier piles in a BNSF rail embankment for a new retaining wall. The shafts were installed from track elevation with the loader and drill straddling train tracks. The job frequently had to halt to allow trains to pass on the neighboring tracks. More than half of the job was not accesible by crane.