  • 1,155 WF Steel Sheet Pile
  • 13 Driven H-Pile

NiCor Gas had undertaken an Environmental Site Remediation project at a former manufactured gas plant in Skokie, IL. Stalworth Underground's scope of services included design, installation, and removal of over 1,500 SF of sheet pile earth retention systems, as well as installation of H-Piles used to support active 36" gas mains.  Excavations on this project reached up to 40 feet in depth.